brand

SATCON

Extra High Voltage Engineering Consultancy Services

  • Engineering Consultant for Design, Engineering and Consultancy Services for Extra High Voltage Substations, Transmission Lines, Electrical Balance of Plant (EBOP) of Thermal Power Plants, Large Electrical Systems (HV/MV) of Steel plants, Coal & Iron Handling Plants & Misc. Industries, Electrical System studies using ETAP 2020.

    Are you looking for Extra High Voltage Engineering Consultancy Services in Kolkata ? We are providing the same for Substations and Transmission Lines upto 765kV Voltage level.

  • Engineering Consultant for Design, Engineering and Consultancy Services for Extra High Voltage Substations, Transmission Lines, Electrical Balance of Plant (EBOP) of Thermal Power Plants, Large Electrical Systems (HV/MV) of Steel plants, Coal & Iron Handling Plants & Misc. Industries, Electrical System studies using ETAP 2020.

    Are you looking for Extra High Voltage Engineering Consultancy Services in Kolkata ? We are providing the same for Substations and Transmission Lines upto 765kV Voltage level.

Nigeria - 330kV, 132kV and 33kV substations - We are glad announce the start of a new project in NIGERIA to Design and Engineer Upgradation of existing 330kV, 132kV and 33kV substations for the "Accelarated Transmission - Distribution projects (DISCO-ENIP) of Kaduna Electric Distribution Company (KAEDC/SS/Lot1). The job has been awarded by a group of Companies in Nigeria.

The scope includes :

1. Replacement of 1x30MVA, 132/33kV power transformer with 1x60MVA, 132/33kV at existing Gusau 132/33kV transmission substation.

2. Installation of 1x150/165MVA, 330/132/33kV Autotransformer, Upgrading 2x60MVA with 2x100/110MVA, 132kV/33kV Power Transformers and Construction of 2x33kV feeder bays at existing Asaba 330/132/33kV transmission substation.

3. Upgrading 2x40/45MVA to 2x100/125MVA, 132/33kV power transformer, Construction of 2x33kV feeder bays, Shifting of 1x132kV terminal tower at the existing Jericho 132/33kV Transmission substation.

4. Installation of 1x100/110 MVA, 132/33kV power transformers and Construction of additional outdoor 3x33kV feeder bays at Ajah 132/33kV Substation.

5. Upgrading of 1x30MVA, 132/33kV power transformer with 1x60MVA, 132/33kV at the existing Itire 132/33kV Substation.

6. Replacement of faulty 1x60MVA, 132/33kV power transformer and Construction of 3x33kV feeder bays and bus coupler at the existing Ijebu Ode substation.

7. Installation of additional 1x60MVA, 132/33kV power transformer, associated substation equipment and Construction of 3x33kV feeder bays at the existing Wudil 132/33kV Substation.

8. Construction of 2x33kV feeder bays at existing Dan Agundi 132/33kV substation.

We thank the group of 5 companies for entrusting us with this project.